The Gullfaks A matingA small christening

Building the base section

person By Ole Jone Eide
When Norway’s largest industrial contract went to a Condeep project, it meant only one thing: this would be big and heavy. The groundwork was laid at Hinnavågen.
— Workers in front of the substructure on Gullfaks C. Photo: Unknown/Norwegian Petroleum Museum
© Norsk Oljemuseum

The contract between Statoil [now Equinor] and Norwegian Contractors (NC) to build the concrete substructure for Gullfaks C was, at the time of signing (February 1986), the largest ever entered into by an industrial company in Norway. It was valued at NOK 2.5 billion. To meet the project deadlines, NC had begun work even before the formal signing.[REMOVE]Fotnote: Risholm, Toril (25 January 1986). “Gullfaks C – the largest and most
expensive in the world. Norwegian Contractors signed a 2.5-billion-kroner
contract.” In: Stavanger Aftenblad, 25 January 1986, p. 6. See also Steen,
Øyvind (1993). “På dypt vann. Norwegian Contractors 1973–1993,” p. 47.
The fact that NC began work before the contract was formally signed had
happened earlier as well; see, for example, regarding Statfjord C:
Meland, Trude. “NC Starts Work on Statfjord C.” In: Industriminne
Statfjord
https://statfjord.industriminne.no/nb/2019/12/03/nc-i-gang-med-statfjord-c/

Construction started at Hinnavågen. The base section consisted of the bottoms of the individual cells and their associated skirts.

By the summer of 1986, Stavanger Aftenblad could report on this “beehive in Jåttåvågen” that “lies with its gaping cells, bearing witness to a level of technology and effort that would relegate nature’s bees to extras,” where NC “orchestrates the puzzle into place in a myriad of concrete, rebar, and steel.”[REMOVE]Fotnote: Hansen, Knut Egil (19 August 1986). “The Beehive at Jåttåvågen.”
In: Stavanger Aftenblad, 19 August 1986, p. 7

 

March 1986: Gullfaks C under construction in dry dock at Hinnavågen. Just behind it, you can see the sloping tower, which is still standing. Photo: Øyvind Hagen/Equinor

Condeep skirts in a new design / skirt piling

The combination of development in increasing water depths and challenging seabed conditions (for example clay and soft sand) placed ever higher demands on the design of the Condeep base sections.

For stability, most platforms of this type needed skirts—structures set into the seabed to anchor and stabilize the rest of the platform, essentially a foundation. Several earlier Condeeps had such skirts made of steel and/or concrete.

In the 1980s, Olav Olsen, Norwegian Contractors, and the Norwegian Geotechnical Institute (NGI) collaborated to develop and test cylindrical concrete skirts as a direct continuation of the cells, and taller than those used previously. This was termed skirt piling and was intended for great depths and unfavorable seabed conditions.

Olav Olsen (with bag), a pioneer in condeep technology. Photo: Unknown/Norwegian Petroleum Museum

Tests conducted in 1985 showed that, for this purpose, such cylinders could be used as extensions of the storage cells. When, during the test, two cylinders 25 meters high (6.5 meters in diameter) were placed on the seabed, they penetrated under their own weight and were further drawn in by negative pressure (suction).

Although the Troll field was foremost in mind during the trials, the first project where the concept was applied was the Gullfaks C platform. It was fitted with skirt piles 27 meters long.[REMOVE]Fotnote: Steen, Øyvind (2002). “Den frie tanke – om kreativ frihet og en
ledende norsk ingeniør.” Lillestrøm: Byggenæringens forlag, p. 105.

The height of the skirts made it challenging to move the base section out of the 14 m deep dry dock. To achieve sufficient buoyancy, air had to be pumped into the underside of the structure. This had been done before but—as with most aspects of this platform—the volume was larger than ever: 350,000 m³ of air.[REMOVE]Fotnote: Norsk oljerevy / Norwegian Oil Review. 1987, Vol. 13, No. 3, p. 26.
Platforms……. https://www.nb.no/items/9d80d3c7cce66b24c00748cb42e71745?page=35&searchText=%22Gullfaks%20C%22

In preparation for the construction project, significant work was carried out to remove 50,000 cubic meters of seabed material to widen the passage from the dock to deeper water in Gandsfjorden. This passage had to be at least 170 meters wide and 14 meters deep.[REMOVE]Fotnote: Norsk oljerevy / Norwegian Oil Review. 1987, Vol. 13, No. 3, p. 36.
“Towards the end of the major orders for NC.”
https://www.nb.no/items/9d80d3c7cce66b24c00748cb42e71745?page=35&searchText=%22Gullfaks%20C%22

Once out in Gandsfjorden, the tow-out could begin toward the deep fjord landscape at Vats, where the main slipforming and the shaft slipforming were to take place.[REMOVE]Fotnote: Steen, Øyvind (1993). “På dypt vann. Norwegian Contractors 1973–1993.” Oslo: Norwegian Contractors, pp. 48–49.

 

An artist's impression of the skirts and storage cells on Draugen. Illustration: Unknown/Norwegian Petroleum Museum
The Gullfaks A matingA small christening
Published 15. December 2023   •   Updated 16. January 2026
© Norsk Oljemuseum
close Close